The principles of qualification and validation which are applicable to the manufacture of medicinal products.
It is a requirement of GMP that manufacturers identify what validation work is needed to prove control of the critical aspects of their particular operations. Significant changes to the facilities, the equipment and the processes, which may affect the quality of the product, be validated. A risk assessment approach should be used to determine the scope and extent of validation.
The key elements of a validation programme be clearly defined and documented in a validation master plan (VMP) or equivalent documents.
The VMP be a summary document which is brief, concise and clear.
The VMP contain data on the following:
(a) Validation policy;
(b) Organisational structure of validation activities;
(c) Summary of facilities, systems, equipment and processes to be validated;
(d) Documentation format: the format to be used for protocols and reports;
(e) Planning and scheduling;
(f) Change control;
(g) Reference to existing documents.
VALIDATION DOCUMENTATION
A written protocol should be established that specifies how qualification and validation will be conducted. The protocol be reviewed and approved. The protocol should specify critical steps and acceptance criteria.
A report that cross-references the qualification and/or validation protocol be prepared, summarising the results obtained, commenting on any deviations observed, and drawings including the necessary conclusions, including recommending changes necessary to correct deficiencies. Any changes to the plan as defined in the protocol should be documented with appropriate justification.
QUALIFICATION
DESIGN QUALIFICATION
The documented verification that the proposed design of the facilities, systems and
equipment is suitable for the intended purpose.
The first element of the validation for new facilities, systems or equipment is design qualification (DQ).
INSTALLATION QUALIFICATION
The documented verification that the facilities, systems and equipment, as installed or
modified, comply with the approved design and the manufacturer’s recommendations.
Installation qualification (IQ) has to be performed on new or modified facilities, systems and equipment.
IQ includes the following:
(a) Installation of equipment, piping, services and instrumentation has to be confirmed to the current engineering drawings and specifications;
(b) Collection and collation of supplier operating and working instructions and maintenance requirements;
(c) Calibration requirements;
(d) Verification of materials of construction.
OPERATIONAL QUALIFICATION
The documented verification that the facilities, systems and equipment, as installed or
modified, perform as intended throughout the anticipated operating ranges.
Operational qualification (OQ) has to be performed after the successful completion of Installation qualification.
OQ includes the following:
(a) Tests that have been developed from knowledge of processes, systems and equipment;
(b) Tests to include a condition or a set of conditions encompassing upper and lower operating limits, sometimes referred to as “worst case” conditions.
The completion of a successful Operational qualification allows the finalisation of calibration, operating and cleaning procedures, operator training and preventative maintenance requirements. It permits a formal “release” of the facilities, systems and equipment.
PERFORMANCE QUALIFICATION
The documented verification that the facilities, systems and equipment, as connected
together, can perform effectively and reproducibly, based on the approved process
method and product specification.
Successful completion of Installation qualification and Operational qualification follows Performance qualification (PQ).
PQ includes the following:
(a) tests, using production materials, qualified substitutes or simulated product,
those have been developed from knowledge of the process and the facilities,
systems or equipment;
(b) tests to include a condition or set of conditions encompassing upper and lower operating limits.
Qualification of established facilities, systems and equipment
Evidence should be available to support and verify the operating parameters and limits for the critical variables of the operating equipment. Additionally, the calibration, cleaning, preventative maintenance, operating procedures and operator training procedures and records should be documented for further use.
PROCESS VALIDATION
The documented evidence that the process, operated within established parameters, can
perform effectively and reproducibly to produce a medicinal product meeting its predetermined specifications and quality attributes.
Process validation applicable to the manufacture of pharmaceutical dosage forms. They cover the initial validation of new processes, subsequent validation of modified processes and
re-validation.
Process validation normally should be completed prior to the distribution and sale of the medicinal product (prospective validation). In exceptional circumstances, where this is not possible, it may be necessary to validate processes during routine production (concurrent validation). Processes in use for some time should also be validated (retrospective validation).
Facilities, systems and equipment to be used should have been qualified and analytical testing methods should be validated.
Facilities, systems, equipment and processes should be periodically evaluated to verify that they are still operating in a valid manner.
Prospective validation
Validation carried out before routine production of products intended for sale.
Prospective validation should include the following:
(a) Short description of the process;
(b) Summary of the critical processing steps to be investigated;
(c) List of the equipment/facilities to be used (including measuring/
monitoring/recording equipment) together with its calibration status
(d) finished product specifications for release;
(e) List of analytical methods, as appropriate;
(f) Proposed in-process controls with acceptance criteria;
(g) Additional testing to be carried out, with acceptance criteria and analytical
validation, as appropriate;
(h) sampling plan;
(i) methods for recording and evaluating results
(j) functions and responsibilities;
(k) proposed timetable.
Using this defined process (including specified components) a series of batches of the final product may be produced under routine conditions. In theory the number of process runs carried out and observations made should be sufficient to allow the normal extent of variation and trends to be established and to provide sufficient data for evaluation. It is generally considered acceptable that three consecutive batches/runs within the finally agreed parameters would constitute a validation of the process.
Batches made for process validation should be the same size as the intended industrial scale batches.
If it is intended that validation batches be sold or supplied, the conditions under which they are produced should comply fully with the requirements of Good Manufacturing Practice, including the satisfactory outcome of the validation exercise, and with the marketing authorisation.
Concurrent Validation
Validation carried out during routine production of products intended for sale.
In exceptional circumstances it may be acceptable not to complete a validation programme before routine production starts.
The decision to carry out concurrent validation must be justified, documented and approved by authorised personnel.
Documentation requirements for concurrent validation are the same as specified for prospective validation.
Retrospective validation
Validation of a process for a product which has been marketed based upon accumulated
manufacturing, testing and control batch data.
Retrospective validation is only acceptable for well-established processes and will be inappropriate where there have been recent changes in the composition of the product, operating procedures or equipment.
Validation of such processes should be based on historical data. The steps involved require the preparation of a specific protocol and the reporting of the results of the data review, leading to a conclusion and a recommendation.
The source of data for this validation should include, but not be limited to batch processing and packaging records, process control charts, maintenance log books, records of personnel changes, process capability studies, finished product data, including trend cards and storage stability results.
Batches selected for retrospective validation should be representative of all batches made during the review period, including any batches that failed to meet specifications, and should be sufficient in number to demonstrate process consistency. Additional testing of retained samples may be needed to obtain the necessary amount or type of data to retrospectively validate the process.
For retrospective validation, generally data from ten to thirty consecutive batches should be examined to assess process consistency, but fewer batches may be examined if justified.
CLEANING VALIDATION
Cleaning validation is documented evidence that an approved cleaning procedure will provide equipment which is suitable for processing medicinal products.
Cleaning validation should be performed in order to confirm the effectiveness of a cleaning procedure. The rationale for selecting limits of carryover of product residues, cleaning agents and microbial contamination should be logically based on the materials involved. The limits should be achievable and verifiable.
Validated analytical methods having sensitivity to detect residues or contaminants should be used. The detection limit for each analytical method should be sufficiently sensitive to detect the established acceptable level of the residue or contaminant.
Normally only cleaning procedures for product contact surfaces of the equipment need to be validated. Consideration should be given to noncontact parts. The intervals between use and cleaning as well as cleaning and reuse should be validated. Cleaning intervals and methods should be determined.
For cleaning procedures for products and processes which are similar, it is considered acceptable to select a representative range of similar products and processes. A single validation study utilising a “worst case” approach can be carried out which takes account of the critical issues.
Typically three consecutive applications of the cleaning procedure should be performed and shown to be successful in order to prove that the method is validated.
“Test until clean”. is not considered an appropriate alternative to cleaning validation
Products which simulate the physicochemical properties of the substances to be removed may exceptionally be used instead of the substances themselves, where such substances are either toxic or hazardous.
CHANGE CONTROL
Written procedures should be in place to describe the actions to be taken if a change is proposed to a starting material, product component, process equipment, process environment (or site), method of production or testing or any other change that may affect product quality or reproducibility of the process. Change control procedures should ensure that sufficient supporting data are generated to demonstrate that the revised process will result in a
product of the desired quality, consistent with the approved specifications.
All changes that may affect product quality or reproducibility of the process should be formally requested, documented and accepted. The likely impact of the change of facilities, systems and equipment on the product should be evaluated, including risk analysis. The need for, and the extent of, requalification and re-validation should be determined.
REVALIDATION
Facilities, systems, equipment and processes, including cleaning, should be periodically evaluated to confirm that they remain valid. Where no significant changes have been made to the validated status, a review with evidence that facilities, systems, equipment and processes meet the prescribed requirements fulfils the need for revalidation.